Freeman defines six stakeholder categories who are able to influence the success of a project. Select THREE
Freeman’s typology identifies categories such as owners, managers, employees, suppliers, customers, and local community as primary stakeholders with influence. From the list provided, owners, suppliers, managers align with that set.
The prediction of tomorrow’s weather is considered to be which type of change situation?
Contained change refers to scenarios where outcomes can be predicted with a degree of probability, though not with complete certainty. Weather forecasting fits this — not fully certain (like closed change), but predictable through data and modelling.
Daniel is a Project Manager and has just run a risk simulation to find out the likelihood of his project taking 3, 4, or 5 weeks to complete. He discovered it is equally likely the project would take any of those durations. What type of distribution is this?
A uniform distribution gives equal probability to all outcomes. Each project duration (3, 4, 5 weeks) has the same likelihood, making it uniformly distributed.
In a large construction project with many stakeholders, which groups would you expect to see represented on the Project Board? Select TWO
For large/complex initiatives, Senior Users and Senior Suppliers are commonly represented (e.g., via user and supplier advisory groups) to reflect those affected and those providing key deliverables.





Prep2Certsis a premium service offering a comprehensive collection of exam questions and answers for over 1400 certification exams. It is regularly updated and designed to help users pass their certification exams confidently.
Please contact info@Prep2Certs.com and we will provide you with alternative payment options.
You can by Contacting our sales team.